RAIL * Bondi Beach extension: promised 1998 for delivery by 2002.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
* Parramatta to Epping link: promised 1998, delivery by 2006.
* Hornsby to Newcastle high-speed: promised 1998, delivery in stages from 2007.
* North West link from Epping to Rouse Hill: promised 1998, converted to North West Metro in March this year. Delivery by 2017.
* Sutherland to Wollongong high-speed: promised 1998, delivery by 2010.
* Hurstville to Strathfield: promised 1998, delivery by 2014.
* Cross City link (including second harbour crossing): promised 2005, delivery by 2017. BUS * Parramatta to Strathfield bus-only transitway: promised 1998, delivery by 2002.
* Parramatta to Blacktown bus-only transitway: promised 1998, delivery by 2004.
* St Marys to Penrith bus-only transitway: promised 1998, delivery by 2008.
* Blacktown to Wetherill Park bus-only transitway: promised 1998, delivery by 2006. TICKETING * Integrated ticketing: promised July 1997 for 2000 Olympic Games.
* Electronic Tcard: contract signed 2003, delivery by November 2006. Contract for $367 million with ERG Ltd dumped in January this year.